- Home
- Departments
- Purchasing
- Bid Results
- Water Park EVA Concrete Conversion Project
Water Park EVA Concrete Conversion Project
Project Name: Water Park EVA Concrete Conversion Project
CITY INTENDS TO AWARD TO LOWEST RANKED BIDDER
(Bid protests must be filed no later than 5 p.m. on the 5th business day after the posting date.)
|
||
Contractor |
Base Bid Total |
Rank |
Kerex Engineering |
$125,310.00 |
1 |
J.J.R Construction Inc |
$133,467.00 |
2 |
Green Valley Landscape |
$134,835.00 |
3 |
Sposeto Engineering Inc |
$136,002.50 |
4 |
Glissman Excavation Inc |
$136,699.10* |
5 |
Burch Engineering & Construction |
$140,100.00 |
6 |
FBD Vanguard Construction Inc |
$144,230.00 |
7 |
Golden Bay Construction Inc |
$166,101.00 |
8 |
Galeb Paving Inc |
$166,235.00 |
9 |
Guerra Construction Group |
$174,675.00 |
10 |
- Mathematically corrected
* Mathematically corrected